Huffman ISD 2016 Bond Status

Huffman ISD Bond/Construction Update

 

  • We broke ground for the canopy/extension for the HHS Agriculture Building the week of Oct. 1, 2016; the canopy and the north wall are scheduled to be completed just in time for the January FFA Show and Sale. 
  • Bids will go out in January, 2017 for the middle school and high school renovations/additions; the projects on both campuses are scheduled to be completed in August, 2017.
  • Land for the new elementary school is located at the southwest corner of the intersection of FM 2100 and Wolf Road – it is the property just past the Huffman Cemetery. 
  • Bids for construction of the new elementary school will go out in May, 2017; completion of the new elementary school is scheduled for August, 2018.